Project Handover Template (Free, Word Ready)
A free project handover template covering status, scope, stakeholders, risks and next steps. Copy it or download the Word version and hand over any project cleanly.

Project handover template
Skip the typing
Vimbre captures tasks, decisions and commitments from your meetings, chats and emails as the project runs, so the handover is already written.
What is a project handover?
A project handover is the moment one person or team passes a project to another. It happens when someone changes role, goes on leave, leaves the company, or when the project moves from build to run. The handover document makes sure the new owner knows where things stand, what is left and what to watch out for.
What should a project handover include?
- A clear overview and what done looks like
- Honest status, including what is late
- Scope, goals and success measures
- Milestones and tasks, each with an owner and date
- Stakeholders and how they like to be updated
- Budget and approvals
- Risks and blockers
- Decisions already made, and why
- Where files, access and tools live
- A short plan for the first week
Project handover report format in Word
A handover report works best as a short Word document with these headings in this order: Overview, Status, Scope, Milestones, Tasks, Stakeholders, Budget, Risks, Decisions, Access, Next steps. Keep it to two to four pages. Use tables for milestones and tasks, and plain sentences everywhere else. Save it as a PDF as well, so it can be shared without edits.
Project handover example
Project: Website redesign From: Maya To: Ben Date: 12 March
STATUS
At risk. Design is done, build is two weeks behind.
MILESTONES
Design signed off | 20 Feb | Done
Build complete | 15 Mar | Late, now 29 Mar
RISKS
Developer availability drops after 29 March. Need a backup by 20 March.
DECISIONS
Launch moved to 5 April. Agreed by the client, 10 March.
NEXT STEPS
Confirm backup developer. Update the client on the new date this week.
Project handover template FAQs
Start with an overview and honest status. Then list tasks, owners, risks, stakeholders and decisions, and add where everything lives. Walk the new owner through it in person if you can.
What is a project handover template? It is a ready made document with the headings a handover needs, so you fill in details instead of starting from a blank page.
What is the difference between a project handover and a project closeout? A handover passes the project to someone who will keep running it. A closeout ends the project and records lessons learned.
How long should a project handover be? Two to four pages for most projects. Longer only if the project is large, and then add a one page summary at the top.
Is there a Word version of this template? Yes, you can download it above or copy the template from this page into Word.
Never write a handover by hand again
Vimbre keeps track of tasks, decisions and commitments as they happen, so a project handover is ready the moment you need one. Try